Lockout/tagout ranked third on OSHA's preliminary FY2026 most-cited list, and year-end shutdowns stack its hardest parts into a few busy days: contractors, group crews, shift handoffs and machines that restart without warning. See what 29 CFR 1910.147 expects for each one.

A planned shutdown is the one time of year when nearly every machine in a plant may be opened up at once. Maintenance crews, outside contractors and temporary help all work side by side, often across several shifts. A Lockout Tagout Required label at each service point reminds everyone that energy control comes before the first panel is removed.

Why shutdowns raise lockout risk

Lockout/tagout is a perennial on OSHA's most-cited list. The preliminary FY2026 figures, covering October 2025 through August 2026, counted 1,863 violations of 29 CFR 1910.147, third behind fall protection and hazard communication. The OSHA Top 10 breakdown covers the full list.

Shutdown work concentrates the situations the standard treats as special cases. Paragraph (f) of 29 CFR 1910.147 has specific rules for outside contractors, group lockout and shift changes, and a year-end outage often involves all three in the same week.

The core sequence still applies

Every job starts with the same steps under paragraph (d), done in order:

Preparation: The authorized employee knows the type and magnitude of the energy, its hazards and how to control it.

Shutdown: The machine is turned off using its established procedure, in an orderly way that does not create new hazards.

Isolation: Every energy isolating device needed is located and operated to cut the machine off from its energy sources.

Lock or tag application: Each authorized employee applies a lockout or tagout device to each isolating device.

Stored energy: Residual or stored energy, such as springs, hydraulics, air pressure and capacitors, is relieved, disconnected or restrained.

Verification: Before work begins, the authorized employee verifies that the equipment is isolated and de-energized.

Release from lockout under paragraph (e) is just as important on the last day of a shutdown. The work area is checked for tools and people, affected employees are notified, and each device is removed by the employee who applied it, except under the standard's specific exception procedure.

Contractors: trade procedures up front

Under 1910.147(f)(2), when outside servicing personnel do work covered by the standard, the on-site employer and the outside employer must inform each other of their lockout or tagout procedures. The on-site employer must also make sure its own employees understand and follow the restrictions of the contractor's program.

In practice, this belongs in the pre-job meeting, not on the morning work starts. Agree on whose locks go where, who verifies zero energy, and how the contractor's crew will know which machines are still live. Plants that share a process area with contractors often post a WARNING DO NOT UNPLUG label on cords and plugs for equipment that must stay powered, such as controls, sump pumps or freeze-protection circuits, so a cleanup crew does not shut off the wrong thing.

Group lockout for crews

When a crew, craft or department services equipment together, 1910.147(f)(3) requires a group procedure that gives each worker protection equal to a personal lock. The standard spells out several elements:

One authorized employee in charge: Primary responsibility for a set number of workers under a group device, such as an operations lock.

Exposure status: A way for that authorized employee to confirm the status of each group member.

Coordination across crews: When more than one crew or department is involved, overall responsibility is assigned so the work is coordinated.

Personal devices: Each authorized employee affixes a personal lockout or tagout device to the group device, lockbox or comparable mechanism when work begins and removes it when work stops.

Shift changes and handoffs

Shutdowns that run around the clock bring another rule into play. Under 1910.147(f)(4), specific procedures are needed during shift or personnel changes so lockout protection continues without a gap, including an orderly transfer of devices between off-going and oncoming employees.

A written handoff log, with a short walk-down of each locked point, helps the oncoming crew see exactly what is isolated. Machines that may cycle on their own once energy returns deserve extra attention. A WARNING Machine Starts Automatically label, an OSHA-style design, flags those hazards for anyone who was not there when the lock went on.

Labels support the program, not replace it

Warning labels are not lockout or tagout devices. Under 1910.147(c)(5), tags and locks must be durable, standardized, substantial and identify the employee who applied them, and tags must carry a legend such as Do Not Start or Do Not Operate. Labels do a different job: they mark service points, remind workers that a procedure exists and warn about automatic starts after power is restored.

Shutdowns are also a good time to walk the line and replace faded or missing labels while guards are off and surfaces are accessible. The machine guarding guide covers where guard and point-of-operation warnings belong.

The standard also requires a periodic inspection of each energy control procedure at least annually under 1910.147(c)(6), done by an authorized employee other than the ones using the procedure. A year-end outage is a natural time to schedule it.

Before you order

Walk the shutdown scope and count every disconnect, valve and service point that needs a lockout reminder, plus every conveyor, robot cell or press that can start automatically. VLG's manufacturing safety labels cover these hazards across a full production line.

VLG labels are Printed in the USA on premium low-shrinkage calendered vinyl with an industrial strength adhesive, made for steel guards, enclosures and painted machine frames. The Lockout Tagout Required and DO NOT UNPLUG labels use ANSI Z535-style layouts. The Machine Starts Automatically and bilingual Conveyor Starts Automatically labels use OSHA-style designs, the conveyor version in English and Spanish. Plants outfitting several lines can order in bulk, and custom wording, such as equipment numbers or isolation point IDs, can be printed to order with clear minimums.

This post is general safety information, not legal advice. Check the full text of 29 CFR 1910.147, OSHA's lockout/tagout resources and any state plan rules that apply to your site.